Over 1.2 trillion VND allocated for land clearance of metro line to Long Thanh Airport
(NLĐO) - According to preliminary estimates, the total budget for compensation, support, and resettlement for the project to extend the metro line to Long Thanh Airport exceeds 1.2 trillion VND.
According to the Land Development Center - Bien Hoa Branch, the project to extend the Ben Thanh - Suoi Tien Metro Line to the Dong Nai City Administrative Center and Long Thanh Airport will pass through five wards: Bien Hoa, Tran Bien, Long Hung, Phuoc Tan, and Tam Phuoc.

Dự án kéo dài metro Suối Tiên về sân bay Long Thành sẽ góp phần giảm tải cho Quốc lộ 51
According to preliminary estimates, the total expected budget for compensation, support, and resettlement for the project exceeds 1.2 trillion VND.
The project passes through five wards with a total length of over 18 km and an expected width of 17 meters. An estimated 527 households will be affected, including 118 households subject to "total clearance" (full land recovery) who must be provided with resettlement housing.
The total land area calculated for compensation and support is approximately 161,000 square meters, primarily consisting of agricultural and residential land. Additionally, about 149,000 square meters of forest land, institutional land, and defense land are not subject to compensation. Areas with a significant number of affected households include Phuoc Tan, Long Hung, and Tam Phuoc wards.
For households required to relocate, resettlement is expected to be arranged within local resettlement areas, mainly in Phuoc Tan and Tam Phuoc wards. In addition to compensation payments, residents will receive support for temporary housing rentals, life stabilization, vocational transition, and relocation costs.
According to the Land Development Center - Bien Hoa Branch, these are only preliminary estimates for the investment preparation phase. Following the field survey (inventory of assets) and the formulation of detailed plans, the costs for compensation, support, and resettlement will undergo further appraisal and approval in accordance with regulations.
Source: https://nld.com.vn/
In late April 2026, during the 3rd (Extraordinary) Session of the XIth Provincial People's Council of Dong Nai (now Dong Nai City), delegates voted to approve the resolution on the investment policy for the project to extend the Ben Thanh - Suoi Tien Metro Line to Long Thanh Airport.
Accordingly, the project spans approximately 44.6km and consists of two sections, with a total investment exceeding 60 trillion VND.
Section 1, stretching approximately 7.4km, runs from Suoi Tien Station to the City Administrative Center. Section 2, covering about 37.2km, extends from the Administrative Center to Long Thanh Airport. The project also includes the construction of stations, depots, and other supporting facilities along the line.
The project will be implemented across various wards and communes, including: Bien Hoa, Tran Bien, Long Hung, Phuoc Tan, Tam Phước, An Phuoc, Long Thanh, and Nhon Trach. The execution period is expected to span from 2026 to 2030.
The metro line extension will enhance transport connectivity between Ho Chi Minh City, the inner-city wards of Dong Nai City, and Long Thanh Airport, contributing to the socio-economic development of the region.